EPC Price Check

Solar panels, heat pumps and insulation in Bayswater conservation area

In the Bayswater conservation area (Westminster), external wall insulation needs planning permission, and so does an air source heat pump on a wall or roof facing the road; one at the back or side, internal and loft insulation and solar panels on a roof slope normally do not. An Article 4 direction published by Westminster covers this area and removes permitted development rights for replacement windows and doors, and other alterations to the house, so there these need planning permission too. The area has 268 listed buildings; on a listed building solar panels and heat pumps are not permitted development at all and need planning permission and listed building consent. 10,657 homes inside the boundary have an energy certificate: 69.1% are solid-wall homes with no wall insulation, 52.8% heat with a gas boiler and 47.2% are rated D–G; 138 have a heat pump. EPC register November 2026; rules as at 21 October 2026.

Data: EPC register November 2026 (latest certificate per home), conservation area boundaries 3 November 2026, permitted development rules as at 21 October 2026 · calculated 5 November 2026 · Methodology and sources

10,657homes with an energy certificate
69.1%solid walls, no insulation
52.8%heated by a gas boiler
138heat pumps

Article 4: An Article 4 direction published by Westminster covers this area and removes permitted development rights for replacement windows and doors, and other alterations to the house, so there these need planning permission too. (168-208 Sussex Gardens, W2; Article 4 Basement Development Permitted Rights Removed; Article 4 Direction Class E To C3 In Central Activities Zone)

What needs planning permission in Bayswater

Work (house, not listed)In a conservation areaRule
Air source heat pump on a wall or roof facing the road, or nearer the road than the housePlanning permission neededPart 14 Class G, G.1(j)
Air source heat pump at the back or side (outdoor unit up to 1.5 m³, MCS Planning Standards, one per house — two on a detached house)No permission needed (permitted development)Part 14 Class G
Solar panels on a pitched roof (up to 0.2 m proud, not above the ridge)No permission needed (permitted development)Part 14 Class A, A.2(c)
Solar panels on a wall, balcony or roof enclosure facing the roadPlanning permission neededPart 14 Class A, A.2(e)
Solar panels on a flat roof (up to 0.6 m above the roof)Prior approval of appearance from the councilPart 14 Class A, condition A(ba)
External wall insulation (render, cladding, timber, tiles)Planning permission neededPart 1 Class A, A.2(a)
Internal wall insulation, loft insulation, cavity wall insulationNot development: no planning permission—
Replacement windows and doors of similar appearancePlanning permission needed (an Article 4 direction here removes this right)Part 1 Class A, A.3(a)

The homes in the area (latest certificate per home, n = 10,657)

WallsHomesShare
Solid wall (brick or stone), no insulation7,36769.1%
Cavity wall, unfilled8137.6%
Other or not known6596.2%
Timber frame3873.6%
Cavity wall, insulated (as built or unspecified)3363.2%
Solid wall, internal insulation3002.8%
Modern wall (U-value from the design)2282.1%
Cavity wall, partly insulated1761.7%
Solid wall, insulated1591.5%
Cavity wall, filled1291.2%
Solid wall, partly insulated800.8%
Cavity wall, internal or external insulation180.2%
Solid wall, external insulation40.0%
HeatingHomesShare
Gas boiler5,62252.8%
Communal heating2,88827.1%
Electric (storage heaters, panels, boiler)1,99318.7%
Heat pump1381.3%
LPG150.1%
Solid fuel (wood, coal)10.0%
Loft / roof insulationHomesShare
No insulation1,47613.9%
Under 200 mm2842.7%
200 mm or more1131.1%
Insulated (depth not recorded)9589.0%
Flat or other home above7,67572.0%
Other1511.4%
WindowsHomesShare
Single glazed4,89245.9%
Double glazed4,67943.9%
Secondary glazing1,0029.4%
Triple glazed840.8%

Energy rating: A 2 (0.0%) · B 382 (3.6%) · C 5,247 (49.2%) · D 3,708 (34.8%) · E 1,163 (10.9%) · F 132 (1.2%) · G 23 (0.2%). Houses and bungalows: 10% of the homes; solar panels on 0.0% of the certificates. Most common build period on the certificates: before 1900. Designated: 1 January 2010.

Compared with Westminster and England

Share of homesBayswaterAll 56 areas in WestminsterEngland
Solid walls, no insulation69.1%66.4%48.7%
Gas boiler52.8%59.2%66.4%
Rated D–G47.2%—56.5%

Caveats

All conservation areas in Westminster · The rules for every conservation area

Guides: Heat pumps · Solar panels · External wall insulation · Replacement windows · Am I in a conservation area? Postcode checker